Back  Print
 
MECHANICAL COMPLIANCE SUMMARY
2021 WSEC Compliance Forms for Commercial Buildings including Group R1, R2, and Group R3 & R4 over 3 stories Administered by: ©2021 NEEA, All rights reserved
Project & Applicant
Information
Project Title Wesley Bradley Park Phase 2 - Care Center - 2021 WSEC For Building Department Use: Date:      Dec 6, 2024
Project Address 707 39th Ave. SE
Puyallup, WA 98374
Applicant Name Jill Krance
Applicant Phone 952-252-4822
Applicant Email jill.krance@INSITEARCHITECT.COM

Mechanical Compliance Summary Scope - Compliance verification provided in this report is limited to code minimum efficiency requirements for mechanical equipment types defined in Tables C403.3.2(1) through C403.3.2(16) of the 2021 WSEC-C. This includes efficiency multipliers for economizer exceptions. Performance criteria for additional energy efficiency and load management measures ARE NOT included in this report. Additional documentation is required to demonstrate compliance with all other provisions of the energy code, including better than code efficiency criteria for Section C406. For questions about this report, contact WSEC Commercial Technical Support at 360-539-5300 or via email at com.techsupport@waenergycodes.com.

General Occupancy All Commercial General Building Use Type(s) Healthcare, Senior Care Community
Building Cond. Floor Area 37,315
General Project Types
New Building
New Building
or Addition
Mechanical Scope
Central Plant Systems
Single Zone Systems & Equipment
Multiple Zone Systems & Equipment
Alteration
Mechanical Scope
Project Cond. Floor Area 37,315
Floors Above Grade 1
Overall Compliance Path General Prescriptive
Mechanical Project Description
VRF System for heating and cooling with two DOAS with ERV to provide ventilation air.
Mechanical Compliance
Scope and Method
Project Type Mechanical Scope Economizer Exception(s)
Applied?
DOAS Ventilation
Provided?
Equipment Efficiency
Compliance Verification
Building Addition Central Plant Systems Yes NA COMPLIES
New Building Single Zone Systems & Equipment Yes Yes COMPLIES
New Building Multiple Zone Systems & Equipment No Yes COMPLIES
Additional Energy Efficiency
Measures (AEM)
      No mechanical additional energy efficiency measures included in project Load Management Measures
(LDM)
HVAC load management
   
Does building include occupancy classifications requiring DOAS? Yes Does project include DOAS equipment? Yes
Based on project scope do TSPR requirements apply? No Do all systems comply with Appendix D standard reference design or qualify for an exception to TSPR? Yes
Scope & Space Conditioning Building Addition - Central Plant Systems Compliance Verification Complies
VRF Multi-Split Systems Category - Heat pump outdoor unit
Cooling Equipment Efficiency Information
System ID Cooling System Type Specific Type Cooling Capacity
(Btu/h)
Econo Exception
Multipliers
(Full/IPLV)
Required Full
Load Efficiency
(Code Min + Econo)
Required Part
Load Efficiency
(Code Min + Econo)
Proposed Cooling
Efficiency
CE Units Proposed Part
Load Efficiency
PL
Units
Efficiency Compliance
Verification
CU-1,2,3,4 VRF air-cooled HP Heat pump w/ heat recovery 216,000 0 0 10.4 13.7 12.7 EER 20.5 IEER COMPLIES
Heating Equipment Efficiency Information
System ID Heating System Type Specific Type Heat Pump
Heating Capacity
(Btu/h)
Cooling Capacity
(Btu/h) (Identical to
Cooling Table)
Required Heat
Pump Heating
Efficiency
Required Low
Water Temp
Efficiency
Proposed Heat
Pump Heating
Efficiency
HE Units Proposed Low
Water Temp
Efficiency
LWTH
Units
Efficiency Compliance
Verification
Equipment Details
System ID Location in Project Documents - Plan/Detail # Quantity of Fan Coil Units in VRF System System/Equip Compliance Path
CU-1,2,3,4 M2.0A, M2.1B, ME1.1 60 General Prescriptive
  WSEC Equipment Efficiency Reference Table: Table C403.3.2(9) VRF Air-to-Air & Water Source Heat Pumps Air-side economizer exception applied?: Exp 1 - DOAS paired with cooling system (Note equip location limitations)
  Economizer Compliance Method: Economizer not required  
Scope & Space Conditioning New Building - Single Zone Systems & Equipment Compliance Verification Complies
Single Zone Air Systems Category - Fan coil unit, hydronic & VRF
Air Systems Summary Information
System/Equip ID Quantity
of Items
Supply Airflow
Control
Ventilation Standard Ventilation CFM
(Total if Multiple
Items)
Ventilation
Air Source
Paired with DOAS
FC-1, 3, 7, 8, 9, 10, 11, 21 8 Constant volume ASHRAE Standard 62.1 1045 Other System
FC-12, 19, 20 3 Constant volume ASHRAE Standard 62.1 350 Other System
FC-13, 15, 17, 18, 22 5 Constant volume ASHRAE Standard 62.1 905 Other System
FC-2, 14, 16 3 Constant volume ASHRAE Standard 62.1 700 Other System
FC-4 Constant volume ASHRAE Standard 62.1 65 Other System
FC-5, 6, 24, 25 4 Constant volume ASHRAE Standard 62.1 470 Other System
FC-A 32 Constant volume ASHRAE Standard 62.1 2720 Other System
FC-B, FC-23 5 Constant volume ASHRAE Standard 62.1 285 Other System
Air Systems & Equipment - Cooling
System/
Equip ID
Cooling System/Equip Type Specific Type Cooling Capacity
per item (Btu/h)
FC-1, 3, 7, 8, 9, 10, 11, 21 Fan coils, hydronic & VRF, cooling VRF 24,000
FC-2, 14, 16 Fan coils, hydronic & VRF, cooling VRF 30,000
FC-4 Fan coils, hydronic & VRF, cooling VRF 9,000
FC-5, 6, 24, 25 Fan coils, hydronic & VRF, cooling VRF 12,000
FC-12, 19, 20 Fan coils, hydronic & VRF, cooling VRF 18,000
FC-13, 15, 17, 18, 22 Fan coils, hydronic & VRF, cooling VRF 36,000
FC-A Fan coils, hydronic & VRF, cooling VRF 8,000
FC-B, FC-23 Fan coils, hydronic & VRF, cooling VRF 6,000
Air Systems & Equipment - Heating
System
/Equip ID
Heating System/Equip Type Specific Type Heating Output
Capacity
per item (Btu/h)
FC-1, 3, 7, 8, 9, 10, 11, 21 Fan coils, hydronic & VRF, heating VRF 27,000
FC-2, 14, 16 Fan coils, hydronic & VRF, heating VRF 34,000
FC-4 Fan coils, hydronic & VRF, heating VRF 9,000
FC-5, 6, 24, 25 Fan coils, hydronic & VRF, heating VRF 13,000
FC-12, 19, 20 Fan coils, hydronic & VRF, heating VRF 13,000
FC-13, 15, 17, 18, 22 Fan coils, hydronic & VRF, heating VRF 40,000
FC-A Fan coils, hydronic & VRF, heating VRF 9,000
FC-B, FC-23 Fan coils, hydronic & VRF, heating VRF 6,700
Air Systems & Equipment Details
System/Equip ID Discrete Area(s) Served Location In Project Documents - Plan/Detail # System/Equip Compliance Path
FC-1, 3, 7, 8, 9, 10, 11, 21 Office, Education, Dayroom, Corridors, Conf Room, Nurse M2.0A, M2.1A, M2.2A, ME1.1 General Prescriptive
  Cooling Capacity Source: CU-1, 2, 3, 4  
  Heating Capacity Source: CU-1, 2, 3, 4  
FC-12, 19, 20 Spa, Office, Director M2.1A, M2.2B, ME1.1 General Prescriptive
  Cooling Capacity Source: CU-1, 2, 3, 4  
  Heating Capacity Source: CU-1, 2, 3, 4  
FC-13, 15, 17, 18, 22 Serving Kitchen, Dining, Chapel, Commons, Dayroom M2.1A, M2.2B, M3.2, ME1.1 General Prescriptive
  Cooling Capacity Source: CU-1, 2, 3, 4  
  Heating Capacity Source: CU-1, 2, 3, 4  
FC-2, 14, 16 Staff Breakroom, Therapy M2.0A, M2.1A, M2.2A, ME1.1 General Prescriptive
  Cooling Capacity Source: CU-1, 2, 3, 4  
  Heating Capacity Source: CU-1, 2, 3, 4  
FC-4 Med Records M2.0A, ME1.1 General Prescriptive
  Cooling Capacity Source: CU-1, 2, 3, 4  
  Heating Capacity Source: CU-1, 2, 3, 4  
FC-5, 6, 24, 25 Storage, Corridor, Laundry M2.0A, ME1.1 General Prescriptive
  Cooling Capacity Source: CU-1, 2, 3, 4  
  Heating Capacity Source: CU-1, 2, 3, 4  
FC-A Units M2.1A, M2.2B, M3.0, ME1.1 General Prescriptive
  Cooling Capacity Source: CU-1, 2, 3, 4  
  Heating Capacity Source: CU-1, 2, 3, 4  
FC-B, FC-23 Units, Office M2.2B, M3.0, ME1.1 General Prescriptive
  Cooling Capacity Source: CU-1, 2, 3, 4  
  Heating Capacity Source: CU-1, 2, 3, 4  
Single Zone Air Systems Category - Heat pump, split & single package, SC, SDHV
Air Systems Summary Information
System/Equip ID Quantity
of Items
Supply Airflow
Control
Ventilation Standard Ventilation CFM
(Total if Multiple
Items)
Ventilation
Air Source
Paired with DOAS Ventilation energy recovery Energy Recovery
Efficiency (%)
DHU-1 Staged volume ASHRAE Standard 62.1 1400 Integral Not provided, not required
Air Systems & Equipment - Cooling
System/
Equip ID
Cooling System/Equip Type Specific Type Cooling Capacity
per item (Btu/h)
Econo Exception
Multipliers
(Full/IPLV)
Required Cooling
Efficiency
(Code Min + Econo)
Required Part
Load Efficiency
(Code Min + Econo)
Proposed Cooling
Efficiency
CE
Units
Proposed Part
Load Efficiency
PL
Units
Efficiency Compliance
Verification
DHU-1 Heat pump, air cooled Split system 120,000 0 0 11.0 13.9 13 EER 16 IEER COMPLIES
Air Systems & Equipment - Heating
System
/Equip ID
Heating System/Equip Type Specific Type Heat Pump
Heating Capacity
per item (Btu/h)
Cooling Capacity
per Item (Btu/h)
(Identical to
Cooling Table)
Required Heat Pump
Heating Efficiency
Required
Low OSA
Temp Efficiency
Proposed Heat Pump
Heating Efficiency
HPH
Units
Proposed
Low OSA
Temp Efficiency
LTH
Units
Efficiency Compliance
Verification
DHU-1 Heat pump, air cooled, heating Split system 124,000 120,000 3.4 2.25 3.7 COP 2.4 COP COMPLIES
Air Systems & Equipment Details
System/Equip ID Discrete Area(s) Served Location In Project Documents - Plan/Detail # System/Equip Compliance Path
DHU-1 Pool M2.1A, ME1.1 General Prescriptive
  Heating Section/Auxiliary Heating Type: Electric resistance (or None) Economizer Compliance Method: Air-side economizer provided
  WSEC Equip Efficiency Reference Table - Cooling: Table C403.3.2(2) Unitary Heat Pumps  
  Proposed Low OSA Temp Efficiency: 2.4 LTH Units: COP
  WSEC Equip Efficiency Reference Table - Heating: Table C403.3.2(2) - Unitary Heat Pumps  
Single Zone Equipment Category - Baseboard & wall heaters
Radiant & Passive Convection Information
System/Equip ID Quantity
of Items
Ventilation Standard Ventilation CFM
(Total if Multiple
Items)
Ventilation
Air Source
Paired with DOAS
ERH-A 2 ASHRAE Standard 62.1 0 Other System
FF-A 4 ASHRAE Standard 62.1 0 Other System
Radiant & Passive Convection Equipment - Heating
System
/Equip ID
Heating System/Equip Type Specific Type Heating Output Capacity
per Item
HC Units
FF-A Wall heaters Electric 3,000 Watts
ERH-A Wall heaters Electric 750 Watts
Equipment Details
System/Equip ID Discrete Area(s) Served Location In Project Documents - Plan/Detail # System/Equip Compliance Path
Scope & Space Conditioning New Building - Multiple Zone Systems & Equipment Compliance Verification Complies